Domanda |
Risposta |
inizia ad imparare
|
|
The actual amount of monies the project has spent to date.
|
|
|
inizia ad imparare
|
|
An approach that relies on historical information to predict the cost of the current project. It is also known as top- down estimating and is the least reliable of all the cost-estimating approaches.
|
|
|
inizia ad imparare
|
|
This estimate is also somewhat broad and is used early in the planning processes and also in top-down estimates. The range of variance for the estimate can be from –10 percent to +25 percent.
|
|
|
inizia ad imparare
|
|
A cost-estimating approach that uses a database, typically software-driven, to create the cost estimate for a project.
|
|
|
inizia ad imparare
|
|
A contingency allowance to account for overruns in costs. Contingency allowances are used at the project manager’s discretion and with management’s approval to counteract cost overruns for scheduled activities and risk events.
|
|
|
inizia ad imparare
|
|
Costs are parallel to each WBS work package. The costs of each work package are aggregated to their corresponding control accounts. Each control account then is aggregated to the sum of the project costs.
|
|
|
inizia ad imparare
|
|
A time-lapse exposure of when the project monies are to be spent in relation to cumulative values of the work completed in the project.
|
|
|
inizia ad imparare
|
|
The cost aggregation achieved by assigning specific dollar amounts for each of the scheduled activities or, more likely, for each of the work packages in the WBS. Cost budgeting applies the cost estimates over time.
|
|
|
Cost change control system inizia ad imparare
|
|
A system that examines any changes associated with scope changes, the cost of materials, and the cost of any other resources, and the associated impact on the overall project cost.
|
|
|
inizia ad imparare
|
|
The cost management plan dictates how cost variances will be managed.
|
|
|
inizia ad imparare
|
|
The monies spent to attain the expected level of quality within a project. Examples include training, testing, and safety precautions.
|
|
|
Cost performance index (CPI) inizia ad imparare
|
|
"Measures the project based on its financial performance. The formula is CPI
|
|
|
inizia ad imparare
|
|
|
|
|
inizia ad imparare
|
|
The difference of the earned value amount and the cumulative actual costs of the project. The formula is CV = EV – AC.
|
|
|
inizia ad imparare
|
|
"This estimate type is one of the most accurate. It’s used late in the planning processes and is associated with bottom- up estimating. You need the WBS in order to create the definitive estimate.
|
|
|
The range of variance for the estimate can be from –5 percent to +10 percent." inizia ad imparare
|
|
The range of variance for the estimate can be from –5 percent to +10 percent. "
|
|
|
inizia ad imparare
|
|
"Costs are attributed directly to the project work and cannot be shared among projects (for example, airfare, hotels,
|
|
|
long-distance phone charges, and so on)." inizia ad imparare
|
|
long-distance phone charges, and so on). "
|
|
|
inizia ad imparare
|
|
Earned value is the physical work completed to date and the authorized budget for that work. It is the percentage of the BAC that represents the actual work completed in the project.
|
|
|
Estimate at completion (EAC) inizia ad imparare
|
|
These forecasting formulas predict the likely completed costs of the project based on current scenarios within the project.
|
|
|
Estimate to complete (ETC) inizia ad imparare
|
|
"An earned value management formula that predicts how much funding the project will require to be completed.
|
|
|
Three variations of this formula are based on conditions the project may be experiencing." inizia ad imparare
|
|
Three variations of this formula are based on conditions the project may be experiencing. "
|
|
|
inizia ad imparare
|
|
Costs that remain constant throughout the life of the project (the cost of a piece of rented equipment for the project, the cost of a consultant brought on to the project, and so on).
|
|
|
Funding limit reconciliation inizia ad imparare
|
|
An organization’s approach to managing cash flow against the project deliverables based on a schedule, milestone accomplishment, or data constraints.
|
|
|
inizia ad imparare
|
|
Costs that are representative of more than one project (for example, utilities for the performing organization, access to a training room, project management software license, and so on).
|
|
|
inizia ad imparare
|
|
An event that will likely happen within the project, but when it will happen and to what degree is unknown. These events, such as delays, are usually risk-related.
|
|
|
inizia ad imparare
|
|
An approach that assumes the cost per unit decreases the more units workers complete, because workers learn as they complete the required work.
|
|
|
inizia ad imparare
|
|
A market condition where the market is so tight that the actions of one vendor affect the actions of all the others.
|
|
|
inizia ad imparare
|
|
The total cost of the opportunity that is refused to realize an opposing opportunity.
|
|
|
inizia ad imparare
|
|
An approach using a parametric model to extrapolate what costs will be needed for a project (for example, cost per hour and cost per unit). It can include variables and points based on conditions.
|
|
|
inizia ad imparare
|
|
Planned value is the work scheduled and the budget authorized to accomplish that work. It is the percentage of the BAC that reflects where the project should be at this point in time.
|
|
|
inizia ad imparare
|
|
The final variance, which is discovered only at the project’s completion. The formula is VAR = BAC – AC.
|
|
|
inizia ad imparare
|
|
Cost reserves are for unknown unknowns within a project. The management reserve is not part of the project cost baseline, but is included as part of the project budget.
|
|
|
inizia ad imparare
|
|
This rough estimate is used during the initiating processes and in top-down estimates. The range of variance for the estimate can be from –25 percent to +75 percent.
|
|
|
Schedule performance index (SPI) inizia ad imparare
|
|
Measures the project based on its schedule performance. The formula is SPI = EV/PV.
|
|
|
inizia ad imparare
|
|
The difference between the earned value and the planned value. The formulas is SV = EV – PV.
|
|
|
inizia ad imparare
|
|
Many vendors can provide what your project needs to purchase, but you prefer to work with a specific vendor.
|
|
|
inizia ad imparare
|
|
Only one vendor can provide what your project needs to purchase. Examples include a specific consultant, specialized service, or unique type of material.
|
|
|
inizia ad imparare
|
|
Monies that have already been invested in a project.
|
|
|
= (BAC – EV)/(BAC – AC). If you want to see if your project can meet the newly created estimate at completion, you’ll use this version of the formula: TCPI = (BAC inizia ad imparare
|
|
= (BAC - EV) / (BAC - AC). If you want to see if your project can meet the newly created estimate at completion, you'll use this version of the formula: TCPI = (BAC
|
|
|
inizia ad imparare
|
|
|
|
|
inizia ad imparare
|
|
Costs that change based on the conditions applied in the project (the number of meeting participants, the supply of and demand for materials, and so on).
|
|
|
Variance at completion (VAC) inizia ad imparare
|
|
A forecasting formula that predicts how much of a variance the project will likely have based on current conditions within the project. The formula is VAC = BAC – EAC.
|
|
|