Domanda |
Risposta |
Alternative dispute resolution inizia ad imparare
|
|
When there is an issue or claim that must be settled before the contract can be closed, the parties involved in the issue or claim will try to reach a settlement through mediation or arbitration.
|
|
|
inizia ad imparare
|
|
From seller to buyer. Price is the determining factor in the decision-making process.
|
|
|
inizia ad imparare
|
|
A meeting of all the project’s potential vendors to clarify the contract statement of work and the details of the contracted work.
|
|
|
inizia ad imparare
|
|
A contract is a formal agreement between the buyer and the seller. Contracts can be oral or written—though written is preferred.
|
|
|
Contract statement of work (SOW also CSOW) inizia ad imparare
|
|
This document requires that the seller fully describe the work to be completed and/or the product to be supplied. The SOW becomes part of the contract between the buyer and the seller.
|
|
|
Cost plus award fee contract inizia ad imparare
|
|
A contract that pays the vendor all costs for the project, but also includes a buyer- determined award fee for the project work.
|
|
|
Cost plus fixed fee contract inizia ad imparare
|
|
A contract that requires the buyer to pay for the cost of the goods and services procured plus a fixed fee for the contracted work. The buyer assumes the risk of a cost overrun.
|
|
|
inizia ad imparare
|
|
A contract type that requires the buyer to pay a cost for the procured work, plus an incentive fee, or a bonus, for the work if terms and conditions are met.
|
|
|
Cost plus percentage of costs inizia ad imparare
|
|
A contract that requires the buyer to pay for the costs of the goods and services procured plus a percentage of the costs. The buyer assumes all of the risks for cost overruns.
|
|
|
inizia ad imparare
|
|
These are costs incurred by the project in order for the project to exist. Examples include the equipment needed to complete the project work, salaries of the project team, and other expenses tied directly to the project’s existence.
|
|
|
inizia ad imparare
|
|
Also known as firm fixed-price and lump- sum contracts, these are agreements that define a total price for the product the seller is to provide.
|
|
|
Fixed-price incentive fee inizia ad imparare
|
|
A fixed-price contract with opportunities for bonuses for meeting goals on costs, schedule, and other objectives. These contracts usually have a price ceiling for costs and associated bonuses.
|
|
|
Fixed-price with economic price adjustments inizia ad imparare
|
|
A fixed-price contract with a special allowance for price increases based on economic reasons such as inflation or the cost of raw materials.
|
|
|
inizia ad imparare
|
|
An “act of God” that may have a negative impact on the project. Examples include fire, hurricanes, tornadoes, and earthquakes.
|
|
|
inizia ad imparare
|
|
These estimates are often referred to as “should cost” estimates. They are created by the performing organization or outside experts to predict what the cost of the procured product should be.
|
|
|
inizia ad imparare
|
|
These are costs attributed to the cost of doing business. Examples include utilities, office space, and other overhead costs.
|
|
|
inizia ad imparare
|
|
From buyer to seller. Requests the seller to provide a price for the procured product or service.
|
|
|
inizia ad imparare
|
|
A letter contract allows the vendor to begin working on the project immediately. It is often used as a stopgap solution.
|
|
|
inizia ad imparare
|
|
A letter of intent is not a contract, but a letter stating that the buyer is intending to create a contractual relationship with the seller.
|
|
|
inizia ad imparare
|
|
A process in which the project management team determines the cost- effectiveness, benefits, and feasibility of making a product or buying it from a vendor.
|
|
|
inizia ad imparare
|
|
The contractual relationship between the buyer and the seller is often considered confidential and secret.
|
|
|
Procurement management plan inizia ad imparare
|
|
A project management subsidiary plan that documents the decisions made in the procurement planning processes.
|
|
|
inizia ad imparare
|
|
A process to identify which parts of the project warrant procurement from a vendor by the buyer.
|
|
|
inizia ad imparare
|
|
A purchase order is a form of unilateral contract that the buyer provides to the vendor showing that the purchase has been approved by the buyer’s organization.
|
|
|
inizia ad imparare
|
|
From seller to buyer. Price is the determining factor in the decision-making process.
|
|
|
Request for Proposal (RFP) inizia ad imparare
|
|
From buyer to seller. Requests the seller to provide a proposal to complete the procured work or to provide the procured product.
|
|
|
inizia ad imparare
|
|
From buyer to seller. Requests the seller to provide a price for the procured product or service.
|
|
|
Risk-related contractual agreements inizia ad imparare
|
|
When the project management team decides to use transference to respond to a risk, a risk-related contractual agreement is created between the buyer and the seller.
|
|
|
inizia ad imparare
|
|
A tool that filters or screens out vendors that don’t qualify for the contract.
|
|
|
inizia ad imparare
|
|
These are used by organizations to rate prior experience with each vendor that they have worked with in the past. The seller rating system can track performance, quality ratings, delivery, and even contract compliance.
|
|
|
inizia ad imparare
|
|
Defines the obligations for the seller, what the seller will provide, and all of the particulars of the contracted work. Terms of reference is similar to the statement of work.
|
|
|
inizia ad imparare
|
|
This takes out the personal preferences of the decision maker in the organization to ensure that the best seller is awarded the contract. Weights are assigned to the values of the proposals, and each proposal is scored.
|
|
|